Belarus’ N-plant fails to meet modern safety standards – Lithuanian experts

Lithuania’s State Nuclear Power Safety Inspectorate (VATESI) said on Tuesday that a working group set up by Lithuania’s authorities for reviewing Belarus’ report had formulated more than 100 remarks and questions regarding the plant’s resistance to extreme events.

Site selection, the key issue for Lithuania, is not covered in the report, which means that this issue and other important issues regarding environmental impact assessment, the quality of construction and future operations, and safety culture remain unanswered, the watchdog said in a press release.

Sigitas Slepavičius, deputy head for nuclear safety at VATESI, said that, in addition to the questions raised by Lithuania earlier and still unanswered by Belarus, the review of the stress test report had revealed certain shortcomings in the project that needed to be removed before the launch of the plant’s first unit.

The Lithuanian working group says that Belarus’ report fails to substantiate the plant’s ability to withstand the impact of a heavy aircraft crash and ensure the independence of the severe accident management system.

Lithuania also questions the plant’s extreme earthquake resistance analysis as it is based on surveys conducted back in 1997.

According to the press release, the stress tests fails to evaluate possible impacts of fires in nearby forests and other hazards, as well as possible flooding after an earthquake that could occur if the plant’s three artificial ponds on the River Neris collapse. The report also fails to substantiate the choice of extreme phenomena and evens for assessment.

Related Post

Lithuania’s remarks and questions will be submitted by Jan. 25 to an international group of experts set up by the European Commission and the European Nuclear Safety Regulators Group (ENSREG).

The Lithuanian authorities and enterprises involved in the review of Belarus’ stress tests report are VATESI, the Lithuanian Energy Institute, VAE SPB, the Ignalina Nuclear Power Plant, the Lithuanian Geological Service, the Lithuanian Hydrometeorological Service, the Foreign Ministry, the Energy Ministry and the Radioactive Waste Management Agency (RATA).

The stress tests were performed by Atomproekt, a subsidiary of Russia’s Rosatom, the Astravyets project’s main contractor, in 2016.

Lithuanian government officials have said that the tests fail to provide answers to certain questions and call for tests to be conducted based on the EU methodology.

In an effort to hinder the project, Lithuania plans to block the import of electricity from the Astravyets plant.

Share

Recent Posts

  • Foreign affairs

“No need to mince words”: an assessment of what Trump’s victory means for Lithuania

"We can shout very loudly, but it won't change the position of the American people,"…

2 weeks ago
  • Latest

Lies, disrespect and mockery: experts assess Blinkevičiūtė’s “gift” to voters without scruples

From mocking messages flooding social networks to harsh criticism from political experts, the decision of…

3 weeks ago
  • Foreign affairs

Another year in the sovereign history of Kazakhstan

Republic Day has been celebrated in Kazakhstan as the main national date since 2022, giving…

4 weeks ago
  • Defence

In the assessment of NATO’s readiness for war with Russia, there is also a warning about the Baltic states: what is the Kremlin’s wild card?

According to Lrytas.lt, the North Atlantic Treaty Organisation (NATO) faces a new geopolitical reality with…

4 weeks ago
  • Tribune

The Citus projects: The Kaip Niujorke by CITUS project continues – the spirit of New York unfolds in Vilnius, and the second phase is launching

In September, Citus – a creative real estate projects’ development and placemaking company – began…

4 weeks ago
  • Latest

These parties will enter the Seimas for the third time in a row. How many votes did they lose, and how many did they gain?

As various parties emerge, disappear or reorganize themselves in the political space, the Lithuanian Social…

1 month ago