The regulator on Thursday approved a report from Lietuvos Energija (Lithuanian Energy) assessing the two alternative sites close to the shut-down Ignalina Nuclear Power Plant (INPP) in the municipality of Visaginas, north-east Lithuania.
“We have reviewed the report, which was assessed in terms of safety, and approved the content of that document,” Asta Mensonė, spokeswoman for VATESI, told BNS.
Two potential construction sites are located within the territory of the INPP: the first one – to the east from the second unit of INPP and the other one – to the west from the facility’s electricity distribution installations.
The government still has to decide whether or not to build a new nuclear power plant in Lithuania. Sources report that the issue is being discussed with project partners, Latvia, Estonia and Japan’s Hitachi.
The Energy Ministry and Hitachi late in July signed a memorandum of understanding for joint actions to establish an interim VAE project company and invited Latvia and Estonia to join in.
"We can shout very loudly, but it won't change the position of the American people,"…
From mocking messages flooding social networks to harsh criticism from political experts, the decision of…
Republic Day has been celebrated in Kazakhstan as the main national date since 2022, giving…
According to Lrytas.lt, the North Atlantic Treaty Organisation (NATO) faces a new geopolitical reality with…
In September, Citus – a creative real estate projects’ development and placemaking company – began…
As various parties emerge, disappear or reorganize themselves in the political space, the Lithuanian Social…