Progress on the construction of the quay and gas pipeline was discussed at the meeting. Rokas Masiulis, head of Klaipėdos Nafta, a company which is carrying out the project, informed the prime minister about technical details and completed tasks. In July, work will commence on the installation of main equipment on the service platform.
“I was informed that Klaipėdos Nafta is seeking to boost construction efficiency. The contractors were asked to work three shifts and assign more employees for the project to be completed in time. All measures have to be employed to prevent any possible risks. Now everything is being done to complete the terminal in time,” Butkevičius said.
The LNG terminal project has to be finished by end of 2014.
"We can shout very loudly, but it won't change the position of the American people,"…
From mocking messages flooding social networks to harsh criticism from political experts, the decision of…
Republic Day has been celebrated in Kazakhstan as the main national date since 2022, giving…
According to Lrytas.lt, the North Atlantic Treaty Organisation (NATO) faces a new geopolitical reality with…
In September, Citus – a creative real estate projects’ development and placemaking company – began…
As various parties emerge, disappear or reorganize themselves in the political space, the Lithuanian Social…