“The test of isolated operation will bring our power system closer to the state we are to experience when desynchronising from IPS/UPS system and preparing for synchronisation with Continental European Networks. We will test our ability to maintain frequency and control the power system independently as well as identify the areas for improvement,” said Daivis Virbickas, CEO of the Lithuanian electricity transmission system operator (TSO) Litgrid, a press release from the company states.
On 31st August the results of the study on preparation for testing Baltic power system were presented to representatives from Lithuanian, Latvian and Estonian TSOs, ministries and regulators.
The international consulting company “Tractebel Engineering S.A.” which carried out the study, analysed different scenarios for testing isolated operation. Differences in electricity demand, operation of renewable energy sources and international power connections, as well as other aspects were included in the scenarios. The studio estimated the best timing for the isolated operation test to be summer of 2019. Technical measures needed to prepare power system for the test were also identified in the study.
“By assessing different scenarios for the test, the study evaluated the flexibility of the Baltic power system. It revealed that the fast and powerful units of Kruonis Hydro Pumped Storage Plant would well adapt to different scenarios of the isolated operation test, although the potential of older ones would be limited in pumping mode. Newer units would not face such limitation. On the other hand, we would face challenges in scenarios where the Baltic electricity system would operate in isolation with all international interconnections switched off, as the combined cycle unit of the Lithuanian Power Plant would not be able to participate in the test in such conditions. This is the only generator in the Baltic States with such technical limit,” says D. Virbickas.
Based on the study, the three Baltic TSOs Litgrid, AST and Elering will agree upon the most appropriate test scenario and a specific date for the test. Then, the preparation for the test will begin: certain equipment will be checked, additional measuring devices installed and personnel trained. Meanwhile, the conditions of the test will be coordinated with those who could be affected: the participants of the power market, the transmission system operators of other countries, power producers.
When the test is carried out the Baltic countries will restrict their connections with neighbouring countries – Russia and Belarus. To meet power demand, Lithuania, Latvia and Estonia will use only domestic power generation sources and HVDC power interconnections. The three Baltic countries will independently maintain the balance and frequency of power.
According to the study, the preliminary costs of the preparation for the isolated operation test would be from EUR 1.28 million. The study on preparation for testing is co-financed by the European Union’s Connecting Europe Facility (CEF).
"We can shout very loudly, but it won't change the position of the American people,"…
From mocking messages flooding social networks to harsh criticism from political experts, the decision of…
Republic Day has been celebrated in Kazakhstan as the main national date since 2022, giving…
According to Lrytas.lt, the North Atlantic Treaty Organisation (NATO) faces a new geopolitical reality with…
In September, Citus – a creative real estate projects’ development and placemaking company – began…
As various parties emerge, disappear or reorganize themselves in the political space, the Lithuanian Social…