“It is very important that the higher gauge vessels can maintain a higher speeds under complex weather conditions and safely reach the port gates. This is a significant step tpowards the 17 meter depth in the future,” said the Klaipėda State Seaport Authority Director General Arvydas Vaitkus.
The initial dredging to a depth of 15.5 meters has been completed, the first steps in delivering a final target depth of 17 meters.
A 1,200 metre section of the external shipping channel has been deepened with more than 51,000 cubic meters of soil excavated.
The Belgian company Jan de Nul N.V carried out the works at a cost of €1.08 million.
The plan is to deepen the port shipping channel to the mouth of the river to the 16.5-17 meters depth until 2018-2020.
15min.lt
On the eve of the Independence Day of the Republic of Kazakhstan, on December 13,…
Kęstutis Budrys, the President's Senior Adviser, who has been nominated for the post of Minister…
In the heart of Bulgaria, the city of Plovdiv reveals a rich tapestry of ancient…
"We can shout very loudly, but it won't change the position of the American people,"…
From mocking messages flooding social networks to harsh criticism from political experts, the decision of…
Republic Day has been celebrated in Kazakhstan as the main national date since 2022, giving…