Last section of NordBalt submarine cable manufactured

Nordbalt jungties kabelis
Organizatorių nuotr.

The total length of the cable which will interconnect the power systems of Lithuania and Sweden is 900km. The remaining 150km section of the cable will be laid on the seabed of the Baltic Sea from April until mid-summer. Two direct current power cables and a fibre optic cable will be laid in one jacket. The process of laying the cable will be monitored and controlled using underwater cameras and diving vehicles. The length of the power link at sea is 400 km.

“Our team of energy specialists and contractors are working according to schedule. The manufacturing of the cable was the key moment of the NordBalt project. The complexity of the project lies not not only in the mode of electricity transmission and technology that we use, but also in many other factors such as the depth of the sea where the cable is being laid,” said Karolis Sankovski, Head of the Strategic Infrastructure Department and Member of the Board of the Lithuanian electricity transmission system operator Litgrid.

The diameter of the submarine cable is over 12 centimetres, with one meter of the cable weighing about 30 kilograms. The cable is enclosed in 11 insulated and protected layers. It was designed to minimize the loss of transmitting the electricity over a long distance. The interconnection of asynchronous power systems of Lithuania and Sweden will be based on this technology as well. This high voltage direct current (HVDC) technology will be used in Lithuania for the first time.

You may like

Be the first to comment

Leave a Reply

Your email address will not be published.


*


RECOMMENDED ARTICLES